Correspondence

Zohnnie Construction Industries, Inc.
P.O. Box 748
Farmington, NM 87499
  • Cell: (505) 860-0077
    Phone: (505) 258-4945
  • Fax: (505) 326-9177
  • Email: zohngirl@aol.com

ZCI, Inc. 2016 Projects  


APS 4/5 Kitchen Fruitland, NM
Demo'ed small office/storage and converted into a new employee Kitchen (break room). Installed new framing, new flexible duct with cone diffuser, installed all plumbing fixtures, drains and water supply lines, garbage disposal, two compartment sink, installed all cabinetry, counter top, and toe kicks. Installed all electrical recepticals, switched, homeruns, light fixures and breakers using APS LOTO system. Installed all drywall, did all sanding, and texture and followed up with primer application, and applied two coat of paint. Installed new cove base. Installed hood range and vents, installed one electrical stove and two new whirlpool refrigerators. Completed December 2016

Gallup Indian Medical Center - 4th Floor East Renovation                   Gallup, NM
ZCI was hired to mobilize for 6 weeks to provide the following: Included as builts, daily logs, progress of work reported daily, daily materials listings. Provided on site project management and actual execution of labor for the following installations: Minor demo at front location next to electrical panels and HVAC and Duct work Demo, concrete prep and concrete demo, concrete reinforcement installations, concrete pour and concrete finish. Steel Metal Framing & layout adjustment & configuration. Set Doors and install doors (9 in total), Prime and paints door frames, install door hardware, installed all metal framing, soffits at ceiling locations, fur outs, installed insulation (roll out), installed electrical wiring, electrical receptacle boxes, switches, homeruns, and breakers, and light fixtures, installed HVAC flex duct, registers, vents and cone diffusers, minor HVAC demo, installed roll out insulation, installed VCT Flooring and cove base, installed acoustical ceiling grid and ceiling tile, did all primer and paint applications to all drywall surfaces, Installed window tinting, and shelving at reception area. Completed November 2016

JAHA Mundo Ranch 52 Subdivision 2016                                                        Dulce, NM
Zohnnie Construction Industries provided project management services for Jicarilla Apache Housing Authority. ZCI Team: Master Plan schedule of activities, Bid Advertisements; Facilitate Pre-Bid Conference; Issue bid addenda; complete bid reviews, Contract Award, Prepare Contract Documents; prepare relevant reports; Project Schedule; Facilitate Meetings; Complete Construction and Progress Inspections; Change Orders, Communications between JAHA and Selected Contractor; Work in Progress; schedule of values; track and review progress payments, field inspections, final payment inspection, close out of project and warranty inspections (6 months and one year inspections). Completed November 2016

National Park Mesa Verde- Bridge Materials                                         Mesa Verde, CO
ZCI provided bridge materials for a historical structure at Mesa Verde national park. Materials: were 22' long DF#1 Rough Cut Logs, 6' DF#1 KD logs, 10' DD#1 KD, and Pole Barn nails with delivery to be FOB.  Completed October 2016.

National Park Service-Hubble Trading Post                                                   Ganado, AZ
ZCI will remove existing system and will provide and install a two new Ductless Dual Zone (heating and cooling) one for Lavatory and one for main office- split system at Hubble Trading Post. One 208/ 230 V single (we assume the existing electrical will be compatible with existing system. All existing copper tubing will be re-used in bid. ZCI preformed daily job site cleanup and haul off to qualified landfill. The wall mounted indoor units will be installed and each will have its own condenser to include all wiring. All electrical work if necessary and connectors re-used of condenser pad for ductless system and wall mounting brackets were also included.  Completed October 2016.

Tohatchi Fence                                                                 Tohatchi, NM
ZCI replace 650 lf fencing on the property of Tohatchi Health Care Clinic. Scope of work included purchase and installation of the following 650 l.f. of Fence fabric at 5' tall, with top rail to divide hospital property from private residences. All associated galvanized posts, gate posts, corner/end posts, 1 four foot wide pedestrian walk posts and line posts per specifications all to be installed at 18-24" depth with quickcrete. Posts will be schedule 30 and line posts will be schedule 20. Install top rail, tension wire will be 11 ga with hog rings for bottom of fence fabric. ZCI will all necessary hardware to install fencing materials: tubing, tension bars, and caps. Gates will be commercial grade and will be framed with tubing, to include hinges and latches for a wide to 4' wide pedestrian walk gate. ZCI demo scope consists of existing barbwire fence and posts. Debris was hauled away to a qualified landfill. Installation will be digging of post hole labor and quickcrete for additional support, installations of posts, rails fence fabric and stretching including gate. Some light grading with bobcat skidsteer. Jobsite will be cleared of all underground utilities. All fence prep at site performed at site.   Completed October 2016.

Tohatchi Firewall                                                                 Tohatchi, NM
ZCI sealed firewall at 14 designated locations per site visit investigations on 6-9-16 at the Tohatchi Health Care Center. ZCI intends to use Fire Barrier sealant caulk at penetrated firewall locations. Fire-Barrier Sealant Caulk will be applied on both sides off wall penetrations. Penetrations that exceed ¾" - 1" will have 5/8" Fire Core Gypsum Board installed per site visit and per code. Work included all labor, tools and equipment, mobilization for above said location. Daily job site clean up to be done of work area and all debris to be hauled off to a qualified landfill.  Completed September 2016.

Jicarilla Health Care Center - Paint                                                                 Dulce, NM
Scope included the painting of 16 exterior hollow metal doors and 665 l.f. of two fence rail system. Paint work , as it relates to exterior doors & tube fencing per site visit. ZCI cleaned and prepped and sanded all metal surfaces (including: doors, frames and 665 of hand rails at 500 N. Mundo Drive.) Door signs to be properly masked off to insure no damages to sign. Three doors were repaired by applying bondo and sanding down to match existing surfaces. All paint surfaces will be prepped and cleaned as needed to receive paints (ALL Paints to be provided by Hospital per Don Smith and additional paint by ZCI and use paint provided by Hospital). All Fence railing will be primed and painte . Rail locations are to be: Front of Parking lot at east side, Staff parking lot stairs at north side (bid includes rust damage repair at this location also), Patient entrance stairs, Patient Handicap ramp, and stairs at playground location.  Completed September 2016.

Gallup Indian Medical Center-Data/IT Building                                              Gallup, NM
ZCI provided electrical and mechanical materials and workmanship at DATA/IT Building for GIMC Located at Gallup NM. ZCI to provide all labor, supervisory labor tools, NO materials, supplied and fabricated all ducting to be installed for two 5 ton HVAC units at roof location. Also did all penetrations at roof locations and completed all duct work connections, electrical work and gas were also supplied to the North RTU and the South RTU. ZCI also provided and installed electrical supplies, conduit etc., transport of equipment, mobilization to site, duct fabrication/order by client for ZCI team to install. ZCI team also installed insulated duct system to central trunk system also fabricated. Scope also included flexible insulated ducts, vents, cone vents, grills, Return Runs and Supply Runs. Fed vents and returns to feed into each designated locations per drawing provided in solicitation. This will include installation of client provided: registers, diffusers, inlet boxes, cone diffusers, flex connections, screws, sealants, vent grates (vents to fit a 2'x2' ceiling grid). ZCI provided all equipment: Ladders, scaffolding, PPE, Safety Gear, Signs, Barricades for vehicles and work area in bid. Labor are for installations only of the following: electrical supply installations, electrical rigid conduit, electrical wiring, breakers, switches, relays, florescent fixtures (2x2 fixtures), and as-builts. All installations will be tested for balance and for proper electrical loads and tested for proper function. Labor Installations are for the following: will be done according to lay out of HVAC Mechanical layout provided.  Completed August 2016.

Nenahenzad Chapter House. Electrical Work                                       Nenahnezad, NM
ZCI installed one electrical heater at north wall location with duct, vent, thermostats and electrical connection at a new location.  Completed August 2016.

NHA Sanostee Unit/Smiley Residence                                                           Sanostee, NM
Worked on a two story vandalized house. Completed minor drywall repairs at Stairwell location, 2 bedrooms, and two exterior door locations (Front and Back). One window was replaced and 3 doors were repairs (Front door, back door and pantry door) included door jamb was removed & replaced, reinsulated, primed and repainted. Kitchen Fire Extinguisher replaced.  Completed July 2016.

Nenahenzad Chapter House. Electrical Work                                       Nenahnezad, NM
ZCI completed electrical repairs and upgrades to Conference/Veterans hall at the Chapter House. Electrical add on were included which resulted into change orders. One change order for electrical receptacle added on to original scope. The majority of bid was installing lights fixtures, installing breakers and testing electrical system.  Completed July 2016.

APS Door                                                                 Fruitland, NM
ZCI did door repairs on a hollow metal door. Included re-installation and also door kick at 4th floor location of Sulfer Lime Building at APS Compound.   Completed June 2016.

National Park Mesa Verde- Windows Job                                                  Mesa Verde, CO
ZCI installed 8 new windows at a Historical Park Staff Quarters Cabin. Windows provided were provided by Park Service. Wall windows will be specified per SOW and provided window specs. Bid included removal of windows and disposal in an qualified landfill outside the park location. Existing trim was removed on an as needed basis and reused. Damaged trim will be replaced (primed and painted). New clads will be installed to include all equipment, tools, labor, materials (Shims, caulk, touch up paint, screws, insulation batting and exterior window sealant) to complete job in a professional workmanlike manner. Additional framework was required at all window locations as windows provided to our team were too small. All windows were trimmed out and completed to proper finish with existing rough opening. All efforts to prevent unnecessary damage will be executed as these are historical quarters.  Completed May 2016.

Main Street Barbershop                                                                 Farmington, NM
ZCI did Acoustical Ceiling Repairs to the Main street Barbershop located on main street in Farmington. Light commercial job. Work included repairs to ceiling grid and ceiling tile and re-installing existing 2x4 florescent drop light fixtures.  Completed May 2016.

VCT Floors & Cubicles                                                                 Tohatchi, NM
The entrance of the Tohatchi Health Care Clinic, ZCI demo'ed existing floors tiles of 650 sq. ft. at entrance location of clinic. Removed and replaced the floor tiles with new spec'ed VCT tiles. This included floor leveling of concrete floor. ZCI crew disassembled and reassembled cubicles from Fort Wingate and transported to Tohatchi Clinic. A three room cubical reception office was installed to receive new patience. Cubical assembled. Installed All Electrical and Data Lines for Phone for computer and phone systems. ZCI built three customized doors for cubicles, included door hardware; locks, hinges and door stop.   Completed April 2016.

NHA Sheep Springs                                                                 Sheep Springs, NM
Demo vandalized unit. Removed and installed all windows and exterior doors, damaged interior doors including all the closet doors and outside closet doors, damaged floor tile, damaged electrical, damaged stucco at exterior, damaged restroom, kitchen cabinets, and drywall repair. ZCO Primed and painted entire interior of home. Repainted stucco at exterior where damage occurred and graffiti occurred. ZCI painted new exterior doors back and front door and two storage doors, all new door hardware at interior. ZCI did drywall repair of the bedrooms, restated the cabinets, painted the interior of the whole house and repainted around the exterior of the house. ZCI fixed plumbing issues in the bedroom and kitchen (new sinks and faucets). ZCI also installed new furnace and new water heater and exterior water spigot repairs. New electrical panel installed and reconnected to NTUA Standards.  Completed April 2016.

APS Four Corners Plant – Warehouse Renovation                                   Fruitland, NM APS hired Zohnnie Construction convert warehouse into office space. ZCI demoed and frame 28 additional offices and was responsible for all electrical, heating and cooling HAVC for building. The required outlets and light fixtures were installed in each office/cubicle area as well as the data connections required for their office space.  Next the acoustical ceiling and VCT flooring was also installed in all 28 offices and common area of APS warehouse.  Completed February 2016.

ZCI, Inc. 2015 Projects


BIA Santa Rosa Day School – Parking Lot Project                                              Sells, AZ
To correct lighting issues for Santa Rosa Day School parking lot Zohnnie Construction designed a layout for the installation of 19 exterior LED light poles.  A concrete base was poured which supports the 10’ light poles.  These light fixtures have new cut-off LED lamination and provides the necessary lighting needed for the Santa Rosa Day School parking lot. Completed December 2015.

Nation Park Services – National Navajo Monument Floor Abatement         Shonto, AZ
All office furniture was removed and entire building was masked off to prepare for abatement on carpet and tile. Flooring was then properly disposed at an EPA waste site.  5,000 sq. ft. of carpet and VCT tile was then installed throughout building and all office furniture was moved back in to building.  Completed December 2015.

Huerfano Chapter – Landscape                                                                   Huerfano, NM Demoed existing trees and shrubs and then prepped landscape to received 6,530 sq. ft. of sod.  Once sod was planted ZCI then selected heat and low water tolerant plants to be planted and arranged in landscaping as well as new threes.  Picnic tables, benches, and trash receptacle were also placed on Huerfano Chapter grounds. Completed October 2015. 

NHA – Region 2 Drywall Scattered Units                                             Various Locations
Zohnnie Construction installed drywall in 7 scattered NHA units throughout the Navajo reservation which consisted of hanging drywall, mudding, sanding, and texturing each unit.   Completed September 2015.

Huerfano Youth Center – Sealant Repairs                                                 Huerfano, NM
Repaired and sealed leak on AC unit to prevent water damage to roofing and interior drywall at Huerfano Youth Center gym. Completed July 2015.

Sky City Community School – Stair Repair                                                 Sky City, NM
Sky City Community School hired Zohnnie Construction to do stair repair to resurface/reface concrete with a broom finish to prevent slipping hazards. Completed July 2015.

Huerfano Youth Center – Repair on Building                                            Huerfano, NM
Zohnnie Construction repaired siding on Huerfano Youth Center building where galvanized propanel was installed and properly insulated. Completed July 2015.

Nenahenzad Chapter – Comfort Station Repairs                                       Fruitland, NM
The Chapter hired ZCI to excavate plumbing lines to gain access to septic tank clean out and to do a water test so toilets and urinals would be in working order.  Removed outside water faucet, water supply line and capped off drain line.  Two broken copper lines were removed and replaced.  Lastly electrical light fixtures were rewired.  Completed July 2015.

NHA Unit – Window Installation                                                              Smith Lake, NM
For this NHA unit the old windows were removed and replaced with energy efficient windows in the kitchen, dining room, and bedroom. Completed June 2015.

Buddie Benally – Waterline Repair                                                 Upper Fruitland, NM
Zohnnie Construction was hired to repair a leaking waterline. Completed June 2015.

NHA Unit – Renovations                                                                              Iyanbito, NM
Renovations for this unit consisted of drywall repairs, texturing, freshly painted walls, and installing new baseboard. All through the unit new passage doors and closet doors were removed and replaced with new passage and closet doors, light fixtures and wall outlets were also installed.  Lastly energy efficient windows were replaced throughout unit and the exterior siding panel was repaired and painted to match existing exterior panel.  Completed June 2015.

APS Four Corners Power Plant – Maintaining Swamp Cooler                  Fruitland, NM
Zohnnie Construction was selected to maintenance swamp coolers at APS Power Plant.  Maintenance consisted of replacing all AC pads, making sure all motors were in proper working order, cleaning and sealing cooler pans, checking belt drives, greasing bearings and any necessary repairs for water supply line. This work was performed at various locations throughout plant site. Completed May 2015.

NHA Unit – VCT Repair & Door Installation                                            Bluffview, NM
1,386 sq. ft. of flooring was removed as well as cove base and baseboard.  The floors were re-leveled and new VCT tile was installed and new cove base and baseboard were also installed. In addition to this work a 6 panel metal door was replaced with new and improved metal door. Completed May 2015.

NHA Unit – Roof and Storage Repair                                                        Bluffview, NM
ZCI located leak in roof, removed shingles and plywood that had water damaged.  Next new decking was installed where leaking was located and roof was re-shingled to match existing roof.  Water damaged drywall was then removed and new drywall hung, textured, and freshly painted.  In addition to these repairs the gutters were also replaced as well as the stove pipe.  Completed May 2015.

NHA Unit – Renovation                                                                                 Chinle, AZ
ZCI professionally removed mold found in an exterior wall due to moisture exposure.  Once mold infested materials were properly removed ZCI reinforce structure of wall by building studs to strength wall support.  The wall was then insulated, installed plywood, fiber board, vapor barrier, and stucco to match. Wall then received fresh coat of paint to match existing exterior walls. Completed May 2015.

NHA Unit – Renovations                                                                             Ganado, AZ
Zohnnie Construction installed energy efficient windows, removed mold in bathroom, repaired drywall, textured and freshly painted bathroom. Sink base in bathroom was replaced and VCT tile was installed.  Completed April 2015.

APS Four Corners Power Plant – Acoustical Ceiling Tiles                       Fruitland, NM
APS hired Zohnnie Construction to remove and replace 962 sq. ft. of ceiling tile in administration building. Competed March 2015.

 NHA Unit – Renovation of Burnt Unit                                                      Tuba City, AZ
This NHA burnt unit that required ZCI to remove and properly dispose of fire damaged drywall, windows, flooring, counters, and cabinets.  Damaged electrical was repair.  New drywall was hung and textured, freshly painted with new flooring installed throughout unit. Windows were also replaced that had either melted or bust due to fire, new appliances and fixtures (i.e. cabinets, counter tops, vanities, etc.) were also installed.  Completed March 2015.

APS Four Corners Power Plant – Double Door Installation                     Fruitland, NM
APS hired Zohnnie Construction to remove existing electronic sliding door and to install manual double doors with heavy duty hardware. Completed March 2015.

Evelyn Tsosie – Roof Repair                                                                      Sanostee, NM
Removed 48 sq. ft. of damage roof deck and then installed of approximately 1,484 sq. ft. of 29 gauge metal propanel. Drywall repairs to the interior consisted of mudding, texturing, and freshly painting walls. Lastly 2 energy efficient windows were installed.  Completed March 2015.

APS Four Corners Power Plant – Restroom Renovations                        Fruitland, NM
ZCI repaired sewage piping under sink in restroom. Remove and replace VCT tile, install cove base throughout restroom and locker area. Replaced and reconstructed wall where urinals are located. Lastly did concrete cut under sink and rebuilt pee trap. Completed March 2015.

APS Four Corners Power Plant – Flooring Installation                             Fruitland, NM
Flooring installation consisted of removing approximately 2,250 sq. ft. of carpet tile, mastic, and cove base.  Parts of the floor had to be re-leveled and installed new VCT tile and cove base to finish. Completed February 2015.

Upper Fruitland Chapter – Abatement                                            Upper Fruitland, NM
Collected abatement samples for Preschool Building at Upper Fruitland Chapter. Completed January 2015.

APS Four Corners Power Plant – Concrete                                                Fruitland, NM APS sidewalks were tripping hazards which had to demoed. Soil was re-compacted and formed to pour concrete sidewalks.  Flume gate and gate drains were also designed for better drainage to prevent sidewalks from buckling and water accumulating and freezing during winter season. Completed January 2015.

NHA Unit – Storage Renovation                                                                      Pinon, AZ
Renovated storage unit which consisted of replacing collapsing ceiling and replaced walls due to root growth that was interfering with storage unit. Ceiling and walls received new drywall, mud, texture and painted to match existing walls.  New hardware was also installed and locks were changed.  Completed January 2015.  

NHA Unit – Flooring Repair                                                                Ojo Amarillo, NM
NHA hired Zohnnie Construction to remove existing tile and repaired subfloor near entrance. Once subfloor was repaired ZCI then installed VCT tile throughout unit.  Completed January 2015.

ZCI, Inc. 2014 Projects


APS Four Corners Power Plant – Roof Repairs
                                       Fruitland, NM APS selected Zohnnie Construction to remove existing roof and install new 26 gauge high rib propanel.  Completed December 2014.

APS Four Corners Power Plant – Door Installation                                   Fruitland, NM
Zohnnie Construction repaired doors, door glass replacement, and install sweepers for APS Power Plant. Completed December 2014.


Newcomb Chapter – Mapping Job                                                             Newcomb, NM
Zohnnie Construction was chosen to create a conceptual map for chapter utilities, sewer and water system, slopes and topography and scared sites.  Completed December 2014.

APS Four Corners Power Plant – Asphalt Striping                                    Fruitland, NM
APS hired Zohnnie Construction to paint yellow striping at APS pedestrian walkways at west parking lot, vendor’s parking lot and trucks at fence line. Completed November 2014.

NHA Unit – Stucco and Block Wall Repairs                                               Tuba City, AZ
ZCI repaired a 6’x 12’ section of brick wall and also repaired the exterior stucco damage. Wall was repainted to match existing wall.  Completed October 2014.

National Park Services – Shade Structure                                                   Flagstaff, AZ
Zohnnie Construction disassembled and relocated shade structures to xeriscape location where shade structure was reassembled.  ZCI supplied and installed new shade structure at visitor’s center. Completed October 2014.

APS Four Corners Power Plant – Renovation                                            Fruitland, NM
Zohnnie Construction installed new cabinets and replace all acoustical ceiling tiles, primed and painted drywall and masonry wall.  ZCI also installed VCT floor tile, cove base, and framed walls to create offices.  Performed finished work for all offices and installed cabinets, countertops, sink fixtures and garbage disposal.  Completed September 2014.

Shiprock VFW – Building Fence                                                                  Shiprock, NM
Shiprock VFW hired Zohnnie Construction to build a fence and to install wide swing gates which included fabric fencing with tall posts and railings to provide privacy.  Completed September 2014.

APS Four Corners Power Plant – Door Repairs                                         Fruitland, NM
Four Corners Power Plant hired Zohnnie Construction to repair 19 doors in 19 different locations throughout the plant. Repairs also consist of door knob, hinge and sweeper replacement. Completed September 2014.

NHA Unit – Renovation Unit                                                               Mariano Lake, NM
Zohnnie Construction renovated unit starting with the stucco repair and painted to match existing exterior walls.  Some interior walls were repaired and painted to match wall color in kitchen, living room, and in all bedrooms.  New flooring was also installed as well as electrical and plumbing repairs.  Completed September 2014.

Cat Creek Southern Ute Indian Tribe - Fence Project                                  Ignacio, CO
Southern Ute Tribe selected ZCI to installed 2.9 miles lay-down fence on cultural sensitive land for at Cat Creek.  Completed August 2014.

APS Four Corners Power Plant – Concrete                                               Fruitland, NM APS hired Zohnnie Construction for concrete work.  4 slabs of concrete were replaced and evened out by grinding, remove and poured one section of concrete approximately measuring 10’x3’. Completed August 2014.
Chinle Chapter – Motor for Furnace                                                              Chinle, AZ
Zohnnie Construction replaced a blower motor in furnace at Chinle Chapter.  Completed August 2014.

NTUA – Perimeter Fence                                                                      Window Rock, AZ
The removal of 475 l.f. of 4’ tall chain link fence was properly disposed at an EPA waste site.  ZCI then installed posts and poles in concrete for the 475 l.f. of 4’ tall chain link fence around the perimeter of building. The chain link fence was lined with fence fabric to provide privacy.  Completed August 2014.

APS Four Corners Power Plant – Building Renovation                              Fruitland, NM
Repaired existing doors as well as install new doors with thresholds and painted newly installed doors. Demoed the interior wall which then received new drywall, texture, and painted to match existing walls and new VCT tile and cove base were installed.  Completed July 2014.

APS Four Corners Power Plant – Plumbing Men’s Restroom                   Fruitland, NM APS hired Zohnnie Construction to clean men’s restroom in the administration building where new flash valves, new gaskets, and vacuum breakers and seals were installed.  Completed July 2014.

APS Four Corners Power Plant - Tile Repairs                                           Fruitland, NM
In the SO2 building need tile installation which required the removed of existing carpet and some tile which was properly disposed at on site trash bins. ZCI had to scrap some mastic and relevel floors to properly install in multiple rooms.  Lastly cove base was installed in all rooms and common area.  Completed July 2014.

APS Four Corners Power Plant – Stair Treads                                           Fruitland, NM
Zohnnie Construction removed old stair treads on concrete stairs and installed new stairway treads on concrete stairs to prevent slipping hazards. Completed June 2014.

APS Four Corners Power Plant – Evaporative Cooler Maintenance        Fruitland, NM
Maintenance swamp coolers at APS Power Plant.  Maintenance consisted of replacing all AC pads, making sure all motors were in proper working order, cleaning and sealing cooler pans, checking belt drives, greasing bearings and any necessary repairs for water supply line. This work was performed at various locations throughout plant site. Completed May 2014.

ZCI, Inc. 2013 Projects


New Comb Chapter                                                                                    New Comb, NM
New Comb Chapter hired Zohnnie Construction to provide a community land-use map for New Comb Chapter in New Comb, NM.  In the map contained chapter bounty area, slope with contours and elevation, BIA study forage/land/status/grazing potential, NHA study, zoning area for community and economic development, power lines, roads, and sacred sites, archeology sites and reference registry for BIA data.  Completed December 2013.

NAPI Executive office Renovation                                                            
Farmington, NM
Renovations on COO and CEO executive offices at NAPI headquarters stared with correcting abandon floor drain which was patched and leveled.  Some dry wall and texture in executive bathroom were repaired as well as installation of new pedestal sink, shower head, and plumbing addressed to accommodate new plumbing upgrades.  In executive offices new coats of paint were applied, new cabinetry and shelving built and new ceiling tile installed in both offices, lastly new wood flooring installed in the executive offices and bathroom.  Completed December 2013.

Gallup Indian Medical Center                                                                         
Gallup, NM
ZCI was responsible for repairs to the concrete landing on the exterior of the Gallup Indian Medical Center which is a multileveled building.  The concrete landings were power washed to wash away loose debris then resurfaced at a number of locations where drainage on landing was pooling.  Lift was used in aiding worker to reach heights and harnessed in at all times.   In addition to resurfacing ZCI also repaired/filed in chunks of that were missing from the concrete landing.  Once repairs were completed every landing was primed and painted on each level of the hospital.  Completed November 2013.

Chinle Health Care Concrete and Drainage                                               
Chinle, NM
To correct drainage problem Zohnnie Construction installed grate drain system which included cutting in to existing concrete sidewalk, re-routing gutter for proper drainage for two commercial buildings.  ZCI installed approximately 140 LF of 4” PVC pipe for commercial buildings.  In addition ZCI designed and installed concrete flume approximately 78 LF. Completed November 2013.

APS SO2 Lunch/Break Room                                                                     Fruitland, NM
Zohnnie Construction installed a temperature unit and door jamb APS Four Corners Power Plant. Completed September 2013.

APS U7 and MTC Shop                                                                             Fruitland, NM
ZCI serviced coolers in U7 and MTC shop which included replacing water pumps, pads, and bearings on wheels.  Completed September 2013.

Chinle Chapter Repairs                                                                               
Chinle, AZ
Air conditioning unit was serviced which included cleaning out coils and unit, changed filters, check refrigerant and etc.  Completed August 2013.

APS NPDES Building                                                                              
Fruitland, NM
ZCI serviced several coolers in NPDES Building which included changing pads and sealing coolers, changing floats, drive belts, motors and broken water lines.  Completed August 2013.

APS SO2 Lime Building Cooler                                                              
Fruitland, NM
Zohnnie Construction installed 25,000 BTU cooler in SO2 Lime Building for APS Four Corners Power Plant.  Completed August 2013.

APS 4/5 LOTO Ceiling Tile                                                                       
Fruitland, NM
Removed and replaced acoustical ceiling tile in 4/5 Control room and AO room.  Completed July 2013.

Nenahnezad  Chapter Roofing                                                                
Fruitland, NM
ZCI provided all labor and material to remove old roofing on approximately 16,000 sq. ft. and repaired soft spot on roof decking at Nenahnezad Chapter house.  New roofing material was installed on all 16,000 sq. ft.. Completed June 2013

Borundo Residence                                                                                 
Farmington, NM
Fifteen window installations and 2 door exterior doors replaced by Zohnnie Construction.  Completed May 2013.

Arviso Drywall 30 units                                                                        
Ojo Amarillo, NM
ZCI installed drywall in 30 units as well as taped, mudded, and textured all 30 units.  Completed May 2013.

Ray the Welder                                                                                       
Bloomfield, NM
Zohnnie Construction installed exterior door and replaced an interior door.  Completed May 2013.

NHA Unit #3                                                                                               
Fruitland, NM
Repaired brick siding and brick porch to match existing brick due to fire damages.  Once repairs were made ZCI painted brick to match exterior paint.  Completed April 2013.

APS  Floor Tile                                                                                         
Fruitland, NM
VCT tile was installed in E & I training room at Four Corners Power Plant.  Completed April 2013.

APS Metal Door                                                                                        Fruitland, NM
ZCI removed and replaced metal door for Four Corners Power Plant in the Lime building.  Completed April 2013.

Tyonek Contractors                                                                                 
Tohajiilee, NM
Zohnnie Construction provided flooring installation for 29 units in Tahajiilee New Mexico. 

NHA Unit #58                                                                                           
Ojo Amarillo, NM
Fire damaged unit required several window installations.  Fascia, gutter and downspouts were also replaced do to fire damage in addition to repairing support beam and soffit panels.  Stucco also sustain fire damage which Zohnnie Construction cut and removed then repaired to paint and  match existing stucco on unit.  Completed April 2013.

NHA Unit #51                                                                                      
Coyote Canyon, NM
Zohnnie Construction purchased and delivered material for unit #51. Completed April 2013.

NHA Vandalized Unit #16                                                                        
Shiprock, NM
ZCI repaired burnt kitchen cabinets, broken drywall damaged, and installed exterior metal door and several interior doors.  Repairs to the bathroom were also done as well as fresh coats of paint applied to entire interior walls.  Completed April 2013.

Navajo Nation Fleet Management                                                           Shiprock, NM
Zohnnie Construction renovated office space for Fleet Management office for the Navajo Nation.  Drywall work, fresh paint, baseboard installation, window installation, and vent and duck work relocated due to fumes entering office space.   Electrical relocations for lighting in office space were also part of renovation.  Completed March 2013.

NHA Crownpoint Housing  #11 Platero Residence                                 Crownpoint, NM Repairs were made to a waterline break in ceiling of residential unit #11.  Line break damaged drywall, popcorn ceiling and insulation at attic location.  Crew removed damaged sheet rock at wall and ceiling location. ZCI team also removed and replaced damaged roll our R-19 Insulation.  Water lines were repaired and soldered by torch.  Tape, texture, prime and two coats of paint were applied for proper finish.  This included baseboards and door casing. Completed March 2013

NHA & Risk Management Unit# 58                                                     Ojo Amarillo, NM
ZCI Removed all damaged exterior materials from Unit 58 due to electrical fire.  Included window replacement, stucco replacement, rigid stucco insulation, stucco netting, porch beams, soffit, soffit vents, fascia boards, gutters and down spouts.  Crew applied brown coat and a texture coat on damaged location at exterior, primed and a two coat paint finish. Completed March 2013

APS Four Corners Power Plant                                                              
Fruitland, NM
Installed new flooring and cove base at EI Training Center while office was operational. Completed March 2013

APS Four Corners Power Plant                                                 
                Fruitland, NM
ZCI removed and replaced existing stair treads and reinstalled new treads at the 4 & 5 Planning Room.  Completed March 2013

Navajo Nation Fleet Management                                                            
Shiprock, NM
ZCI renovated a 2nd floor office for The Shiprock Fleet Management. Remove and replace flooring as well as cove base, installed a new window with associated proper framework, interior framing for new floor lay out and removal of metal stairs for attic access. Scope included electrical upgrades for more wall receptacles to accommodate incoming office equipment, ceiling fan, and relocated carbon monoxide vent unit to mezzanine.   Team also removed and replaced damaged dry wall, re-prime, re-texture and re-paint throughout Fleet Managers Office.  Completed March 2013

APS Four Corners Plant                                                                       Fruitland, NM Fabricated and installed new cabinet drawers and hardware for Power Plant Control Room at 4/5 building (two locations). Completed February, 2013

BIA SWRO- Fort Wingate Elementary School Canteen Renovation    Fort Wingate, NM
Scope of work was for a classroom conversion to canteen for dormitory students. This was a renovation job with electrical upgrades to service refrigerator, electric stove, popcorn maker and hood vent.  Plumbing upgrades to service new sink, garbage disposal and ice machine. Additional work included demo, light carpentry, cabinet installation, drywall repairs, paint and texture.  Completed February, 2013

NHA - Unit #16                                                                                       Shiprock, NM
Renovated vandalized unit as it relates to: drywall repairs, tape and texture, primer and paint, removal and replacement of windows and window screens, replace broken cabinetry, stain cabinetry, interior door removal and replacement, finish paint as it relates to interior doors, and trimwork and bathroom repairs.  Completed January, 2013

San Juan Districts Attorney's Office - Concrete Stairwell Staining    Farmington, NM
Completed flooring finish work as it relates to concrete staining and concrete sealing throughout various locations in San Juan County building. Use of ECO Products as project was a LEED Project. Area was two stairwells and 9 utility locations for flooring finish. 
Completed January, 2013

ZCI, Inc. 2012 Projects


NHA Pinon, AZ Warehouse – Concrete Building Foundation Slab, Sidewalk, Curbs & Gutters                                                                                                              Pinon, AZ
For the construction of a new warehouse for Navajo Housing Authority, the ZCI crew completed excavation, steel reinforcement, and installation of new concrete piers, stem wall, and slab for building; and completed same for propane tank, and sidewalk, and curb and gutter installation.  Crew also installed two new 24’ wide x 6’ height double swing gates, concrete parking bumpers, safety bollards at overhead door entries, and splash guards.  Completed November, 2012

National Park Service - Abatement Project                                                  Holbrook, AZ
ZCI completed a floor tile and floor mastic abatement project for National Park Service Petrified Forest at the Staff Quarters, Unit #208, the Administration Building women’s public restroom, and the furnace room for the Park Administration Building.  One drywall abatement test was conducted in the pre-existing 1978 unit for asbestos in drywall, and joint compound (Unit#208).  Completed November, 2012

APS Four Corners Plant – Building #30                                                     Fruitland, NM
Commode removal and repairs:  Excavate and trench to expose cast iron plumbing and replace with a new sleeve, concrete foundation floor repair, replace abated floor tile, drywall repairs, tape and texture,  prime and two coats of paint for proper finish. Completed November, 2012

Morgan Residence/Riverside Chapel                                                         San Juan, NM
Custom built a handicap ramp and porch deck as a charitable donation. Completed November, 2012

Benally Residence – Ducting Repairs                                          Upper Fruitland, NM
ZCI provided materials, equipment, and labor to complete duct work repairs, build an air conditioner stand, and minor electrical work for bathroom.  Completed November, 2012

Jicarilla Agency Office - BIA SWRO                                                       Dulce, New Mexico
ZCI installed approximately 120 l.f. of concrete sidewalk and concrete walk-up pads, modified existing ADA ramps and rails, custom built a porch deck cover, and installed an interior cashier’s window for the Accounts Receivables Department.  Completed November, 2012

BIA SWRO - Southern Ute Agency Forestry Division - ADA  Ramps             Ignacio, CO
ZCI weatherized three windows in a modular unit, re-leveled a modular office with blocks and piers, installed a stick-built, framed skirting with pro-panel veneer, and installed a custom-built 35” long ADA handicap ramp. All materials were welded and galvanized metal, as per design specifications.  ADA ramps had concrete piers for support. This included all concrete work to finish the job.  Welded ramp was primed and painted with DTM paint. Completed October, 2012

APS Four Corners Plant – APS Administration Building                               Fruitland, NM
Minor renovations to electrical, acoustical ceiling, door installation, installed VCT tiles over abated flooring, cove base, trim work finish,  applied primer and  two coats of  paint to finish.  Completed October, 2012

NHA Risk Management – Unit #37                                                          Ojo Amarillo,  NM
Scope of work included vandalism removal and clean up, repairs to drywall at interior of  a 4 bedroom home, tape and texture, prime and paint for interior, removal and replacement of all windows, installation of cabinetry, removal and replacement of all damaged interior and exterior doors and closet doors.  Completed  October,  2012

Eaton Task Order 3:  Chg. Order - Weatherization Upgrades for NTUA     Shiprock, NM 
Install approximately 6,000 sq. ft. of 2” foam insulation at the Shiprock Fleet Management Office.  Change order was added to Task Order 3.  Included site prep (masking off and taping off), foam installation, caulking skylights, equipment rental/lift, and proper disposal of job site refuse.   Completed September, 2012

NHA Fort Defiance Office – Inspection                                                    Fort Defiance, AZ
Scope of work included gas line inspection and pressure testing. Also included were furnace and cooling unit inspections and reporting of compliance to NTUA office.  Completed October,  2012

Eaton Task Order 5 - (Energy Audit) for NTUA/NTTU                         Fort Defiance, AZ
Weatherization and energy upgrades were as follows: Installation of thermostats (ECM 3), programmed thermostats, insulate water heaters with heater jackets (ECM 13), insulation upgrades (blown-in insulation and foam insulation to achieve R-42 aka ECM 7), replace aerators with 1.0 gpm aerators in lavatory, replace kitchen aerators with 1.5 gpm aerators, and replace showerheads with 2.0 gpm aerators (aerators were ECM 12).  Weatherizing windows and doors (ECM Weatherization). This scope performed in 28 buildings in Fort Defiance, Arizona.   Completed September, 2012
Facilities Maintenance Appliance Shop
            Facilities Maintenance Office and Shop
            Fire Station District #1
            Food Distribution
            Fort Defiance Agency Office
            Forestry Compound Administration
            Forestry Compound Office and Equipment Room
            Forestry Office/Shop
            Forestry Laboratory
            Fort Defiance Agency Housing Service
            Head Start
            Financial Warehouse
            Modular Office Unit/NDWD
            Property Management Office/Warehouse #1
            FD Administration Building
            Ft. Defiance Engineering Trailer
            Ft. Defiance Double Wide Office Trailer
            Ft. Defiance Operations Building Modular
            Headquarters Administration Building
            Headquarters Computer Service Building
            HQ Engineering Building
            HQ Form Laboratory (Training)
            Headquarters Meter/Transformer Shop
            Headquarters New Modular Laboratory
            Headquarters Property/Facility Management
            Headquarters Records Management
            HQ Safety/Communications Building
            HQ Utility Construction Department Building (Scada)

Eaton Task Order 4 - (Energy Audit) for NTUA/NTTU                                   Kayenta,  AZ
Weatherization and energy upgrades were as follows:  Installation of thermostats (ECM 3) and programmed thermostats at the Judicial Building (Tribal Office Building).  Completed September, 2012

Eaton Task Order 2 - (Energy Audit) for NTUA/NTTU Shiprock, NM & Teec Nos Pos, AZ
Weatherization and energy upgrades were as follows: Installation of thermostats (ECM 3), programmed thermostats, insulated water heaters with heater jackets (ECM 13), insulation upgrades (blown-in insulation and foam insulation to achieve R-42,  aka ECM 7), replace aerators with 1.0 gpm aerators in lavatory, replace kitchen aerators with 1.5 gpm aerators, and replace showerheads with 2.0 gpm aerators (aerators were ECM 12).  Scope was performed in 14 buildings in Chinle, Pinon, and Tsaile,Arizona. Completed September,  2012
Agency Veterans Affairs Office
            Chinle Senior Citizens Building
            Fire Station Building
            Hayool Kaal Hooghan Regional Treatment Center
            Housing Services Office
            Judicial Building
            Labor Relations/Property Office Building
            Motor Pool Building
            Tribal Offices Building
            Water Resources Office and Warehouse
            WIC Modular Clinic
            Chinle Vehicle Shop
            Modular Office Building in Pinion
            Tsaile WIC Building

BLM Moab, Utah Fire Operations – Storage Shed Kits                                    Moab, Utah
ZCI sold and delivered two metal storage shed kits to the Moab, Utah Fire Operations Center.  Sheds Measured 20’ width x 14’ depth x 10’ height and engineered for wind load up to 70mph;  a roof pitch of 3/12 engineered for load of 30 psf.  Completed September, 2012

Santa Clara Day School - Evaporative Coolers & Furnaces Job                   Espanola, NM
ZCI upgraded the school’s evaporative coolers, furnaces, heating units for 10 buildings of the Day School campus.  This included all labor, materials, equipment (lift equipment), mobilization, test run of units (start up and check out of each unit), and replacement of bad motors/pumps/floats in two cases. Total area of upgrades and repairs 22,990 sq. ft.  Completed September, 2012

Eaton Task Order 3 - Energy Audit NTUA/NTTU Shiprock, NM & Teec Nos Pos, AZ Weatherization and energy upgrades were as follows:  Installation of thermostats (ECM 3), programmed thermostats, Insulated water heaters with heater jackets (ECM 13), insulation upgrades (blown-in insulation and foam insulation to achieve R-4, aka ECM 7), replace aerators with 1.0 gpm aerators in lavatory, replace kitchen aerators with 1.5 gpm aerators, and replace showerheads with 2.0 gpm aerators (aerators were ECM 12).  This scope performed in 16 buildings between New Mexico and Arizona. Completed August, 2012
            Navajo Food Distribution Warehouse
            Shiprock Day Care Center
            Headstart/Agricultural/ Communications Services/Legal Aid Building
            Judicial Building
            Nutrition Building
            Property/Uranium Mine Workers Building
            Public Safety Building-Headquarters
            Transportation Shop
            Water Resources Building (shop and garage)
            Nageezi Sub-Office
            Shiprock Administration Building
            Shiprock Crew Building
            Shiprock Vehicle Shop
            Teec Nos Pos-Donated Food Warehouse
            Teec Nos Pos-Post Office
            Teec Nos Pos-Water Resources Office

APS Four Corners Plant – Electrical Work for Warehouse                    Fruitland, NM
Electrical work for 480/277 volt heaters in Warehouse for 120 volt line (volt line thermostats).  Client provided control boxes and thermostats and conduit.  ZCI installed 120 volt switching operation for battery chargers.  Three contactors installed and one transformer to  aleve ARC Fault potential. Completed  July, 2012

APS Four Corners Plant – HVAC Services for Multiple Units and Buildings
Fruitland, NM
ZCI serviced two units at 1 & 2 480V Room.  Servicing included inspection, cleaning, pad replacements, cleaning water distribution tubes, replacing various water lines to cooling units, replacing floats
Serviced units at 1,2,3 Maintenance Building, the E & I Shop, and 480V rooms. Bearings were greased in all units, and leak penetrations (boots) were sealed.  Coolers received new belts, floats, brackets, and new pumps, where required, for smooth operation. Replaced compressors as needed, patched pan leaks or replaced pan, and test start each unit. Completed on July 2012

Cochise Contractors -- Giant Convenience Store HVAC Upgrades                 Kayenta, AZ
We installed one RUUD 4 ton cooling/100,000 BTU heating unit, and one RUUD 3 ton cooling/80,000 BTU heating unit for existing convenience store and new building addition.   New ducting, diffusers, and roof jack for new addition were installed.  ZCI extended the line to provide fuel to the new units, and provided 2 new thermostats and wiring to the new units.  Test runs were completed.  Completed August, 2012

APS Four Corners Plant – HVAC Service at APS Warehouse                       Fruitland, NM
For this project, ZCI crew (accessed approximately 10 swamp coolers) for malfunction or worn parts, and performed various repairs and replacements for each cooler.  Each cooler received new pads, and rusted pad doors were replaced on as needed basis.  Bearings were greased in all units, and units that required sealing were done at leaking bases.  Coolers received new belts, floats, brackets, and new pumps, where required, for smooth operation. Replaced compressors as needed, patched pan leaks or replaced pan, and test start each unit. This was a 2 week project that required detailed LOTO Process for security and safety. Completed May, 2012

Empire Machinery – Employee Home Renovations                                          Kayenta, AZ
This project included several repairs and improvements to the exterior of this unit including:  patching holes at various locations on the siding, installing 165’ of skirting to enclose the area underneath the home after removing animal feces from area, installing a fence gate at the west end of unit, and repainting the exterior of building.  ZCI crew also repaired and replaced damaged insulation at various spots underneath
the mobile home.  A complete prime and paint job to exterior of unit. Completed July, 2012

NHA- AC Units Repair for Facility Maintenance Building                      Ojo Amarillo, NM
ZCI was hired to troubleshoot two malfunctioning A/C systems.  We installed missing contactor on the North unit, replaced thermo-static expansion valve, and recharged the unit with new R-22 refrigerant.  On the south unit, we replaced the condenser fan motor, belt, pulley, re-wired the control circuit, and fabricated new cap for exhaust valve fan termination.  An expansion valve cage was also repaired.  Test runs were completed. Total area was 5,500 sq. ft.  Completed  July, 2012.

Cochise Contractors – New Plumbing for Interior Remodel                            Blue Gap, AZ
ZCI installed a new floor sink, new hot and cold water supplies for stackable washer/dryer, a new water heater and PVC pipes, and a new high-flow filtration system for coffee and soft drink dispensers.  ZCI was responsible for all phases of new plumbing system, demolition, rough-in, top-off, and finish.   Completed June, 2012

Cochise Contractors – Store HVAC/Plumbing/Electrical Upgrade                Kayenta, AZ
For this project, ZCI provided all materials, equipment, and labor to excavate trenches to install new underground drain lines from the existing building to within 25’ of the new bathroom addition, 5 new ADA flush valve toilets, 2 new urinals, 4 drop-in lavatories, and 2 exhaust fans.  Demolished old plumbing and installed new Plumbing (rough in, top off, and finish).  Installed HVAC for new remodel Giant and did all phases of HVAC and related insulated duct work and balancing. All fixtures were properly installed, systems started up and checked, and trenches backfilled.  Completed July, 2012

SUIT Heating Duct Service  for Modular Office                                          Ignacio, CO
Two runs of heat ducting located under an modular office were cleaned by crew.  Ducting measured approximately 7” x 20” x 70’.  Furnace was also cleaned as well as evaporative coils.  Completed June, 2012

SUIT Leonard C. Birch Building – New Concrete Sidewalk                              Ignacio, CO
ZCI crew removed existing decorative red stone, gravel, and grass at the north side of building; materials were disposed of at approved waste site land fill.  Crew then used a bobcat to further prep the site, and installed ¾” base and compacted base coarse.  Forms were set and #3 grade 60 rebar was installed at 2’o.c. each way and saddle tied.  Rebar was doweled into existing stand-up curb every 4’.  Concrete sidewalks installed of approximately 75’ length x 5’4” width, and then, 15’ length x 4’ width.  4,000 psi concrete with ¾ rock and 4” slump was poured, stress joints installed every 5’, and the surface given a broom finish for traction.  Completed June, 2012

APS Four Corners Plant – HVAC Service at APS Compound                        Fruitland, NM
For this project, ZCI crew assessed 32 swamp coolers (in 5 building locations on APS compound) for malfunction or worn parts, and performed various repairs and replacements for each cooler.  Each cooler received new pads, and rusted pad doors were replaced on as needed basis.  Bearings were greased in all units, and 4 units required leaking bases to be sealed.  Coolers received new belts, floats, brackets, and new pumps, where required, for smooth operation. Replaced compressors as needed, patched pan leaks or replaced pan, and test start each unit. This was a 6 week project that required detailed LOTO Process for security and safety. Completed May, 2012

APS Four Corners Plant – HVAC Service at Maintenance Tool Room        Fruitland, NM
Project included installing new pads, pump, float, and motor capacitor.  ZCI repaired leaks on cooler, repaired the pad covers, and checked supply line integrity.  Completed May, 2012

Cochise Contractors – Heating Unit Installation    (Plumbing & HVAC)        Blue Gap, AZ
ZCI provided labor and materials to remove and install upgraded new RUUD 75,000 BTU horizontal heater/cooling system for new store and for a new bathroom addition.  New insulated ducting installed as well as diffusers.  New gas line was installed to the newly remodeled location. Completed May, 2012

Benally Residence – Residential kitchen renovation                          Upper Fruitland, NM
ZCI provided materials, equipment, and labor to modify and install new kitchen cabinets, a new stove hood and vent, and to complete minor plumbing repairs.  Completed April, 2012

APS Four Corners Plant – 4/5 Maintenance Shop Breakroom                      Fruitland, NM
Our crew built interior wall stud frame out and door header to accept new 30” pre-hung door.  New drywall was installed, taped, mudded, textured, and sanded.  New door casing was installed.  New walls were primed and painted per specifications.  ZCI installed new cove base at wall perimeter.  Completed April, 2012

BIA Education Dept. Units 28 and 32 – HVAC Repairs and Maintenance    Shiprock, NM
Scope of work included cutting two access holes in the existing furnace to enable cleaning, installing new filters, cleaning and reinstalling vents, cleaning out system ducts and dryer ducts.  Completed April, 2012

APS Four Corners Plant – Doors Replacement (5 Plant Sites)                      Fruitland, NM
            1.  Administration Building - ZCI replaced basement doors with new closures, seals, and                  weatherstripping.
            2.  Unit 4/5 Basement – 3’ x 7’ commercial grade passage door and closures installed.
            3.  Unit 4/5 SO2 Lime/Sulfur Building – Eight feet height double-doors were replaced,                       along with closures, seals, and new sweeps.
            4.  SO2 ABS Building – New LCN door closure was installed with new GRB 30 passage                  knob; the mortise lock was also replaced.
            5.  Unit 1, 2, 3 Scrubber Service Water Building #17 – Two 30” wide doors and one 36”                  wide door were replaced with new closures, sweeps, and thresholds.                                    Completed April, 2012

APS Four Corners Plant – Unit 4/5 Maintenance Shop Break Room     Fruitland, NM
ZCI removed old tile flooring and old cove base.  Subfloor was prepped and leveled to receive new VCT floor tiles.  Transition strips and new cove base were installed.  Minor drywall repairs and patches were completed and walls prepped to receive one new coat of primer and two new coats of latex paint.  All wall décor and furniture was replaced in original positions.  Completed April, 2012

APS Four Corners Plant – Administration Building                                    Fruitland, NM
ZCI completed demolition of a non-load bearing wall of the basement I.T. Field Service area.  Our crew completed small frame-out and header installation at demo location.  Scope of work included minor caulking, installation of the casework, painting, and installing a transition strip on floor.   ZCI supplied all labor, materials, tools, and equipment to complete this project.  Completed April, 2012

Navajo Housing Authority – Norton Residence                                          Pinedale, NM
ZCI, Inc. provided renovation services for this residential unit, including removing broken windows and screens, front entry door, damaged closet doors, damaged plumbing pipe, damaged electrical wiring and light fixtures, damaged smoke detectors, kitchen cabinets and countertops, a damaged support pillar, and damaged drywall.  All of the above items were replaced with new fixtures, materials, and equipment.  New drywall was taped, mudded, textured, primed, and painted with two coats of interior paint.  Damaged wood flooring was repaired or replaced as required.  Completed April, 2012

NAPI – Region 2 – Containment Slab                                                    Farmington, NM
Design and construction of a concrete containment slab to contain a 500 gallon oil tank at NAPI Region 2 Shop.  Work included:  line locate, dirtwork, excavation, rebar placements, formsetting, concrete pour and finish.  Upon cure, ZCI team stripped forms and backfilled site.  Completed March, 2012

APS Four Corners Plant – Unit 4/5 Building                                              Fruitland, NM
Provided interior framework for a new wall to create a new office at Unit 4/5 (Maintenance Building); included drywall work, mud, sanding, texture, installation of door, prime, paint and finish work.  Completed March, 2012

APS Four Corners Plant -- Men’s Locker and Scrubber Room                   Fruitland, NM
Renovation/upgrade for the Locker/Scrubber Room at APS compound.  Scope of work included site prep work, primer, paint, and installation of acoustical ceiling system.  Electrical lighting upgrades and line connections.  Completed March, 2012

Leupp Schools, Inc.- FACE Program – Playground and Fencing Installation  Leupp, AZ
Light earthwork and site clearing, grubbing, installation of 237 lf. chain-link fence for new playground site, installation of playground equipment, swing set, timber boarders, and rubber mulch.  Completed March, 2012

NHA Risk Management – Housing Renovations and Repairs           Mariano Lake, NM
Scope of work included vandalism removal and clean up, included roofing repairs, replacement of roof decking  and new roofing system, insulation installation, plumbing repairs, install HVAC system, electrical wire removal and replacement, interior light fixtures, installation of drywall at interior, tape and texture, prime and paint for interior, removal and replace all windows, installation of cabinetry, remove and replace all interior doors and closet doors, install VCT tile flooring throughout home, installation of all plumbing finishes, interior trim finishes (base boards, etc).  Completed March, 2012

Navajo Nation Division of Wildlife – Metal Building                             Nenahenzad, NM 
Design Build for a 1500 sq. ft. Warehouse.  This project included site excavation, installation of a 30’ x 50’ concrete slab with stem walls and piers to support construction of a new commercial metal building located at the Nenahenzad Chapter House property.  This included the erection of a Metal Building approx 16’ tall, Installing the Red iron framework, installing all electrical fixtures, outlets, wiring  and service box installation, installing two mechanical bay doors, installing the pro-panel skin, 6 skylights, trim out at exterior, and roofing system.  All work was designed by ZCI and Self Performed by ZCI Team. Completed February, 2012

APS Four Corners Power Plant -- Clinic Renovations                               Fruitland, NM 
Interior renovations for APS Clinic.  Scope of work included  furniture removal, cabinetry dismantle,  cove base removal and re-installation, drywall patch and repairs,  including texture, prime and paint interior walls, install cove base, re-install cabinetry, and relocate office furniture back to its original locations. Completed February, 2012

Navajo Housing Authority -- Unit #8 Repairs                                          Ojo Amarillo, NM
ZCI performed stucco damage repairs, fascia repairs. Prime and paint to match existing color and also did some structural repairs to framework for residential unit #8.  Completed February, 2012

Navajo Housing Authority -- Unit #22 Repairs                                     Ojo Amarillo, NM
ZCI performed stucco damage repairs from a fire at one end of the home.  ZCI replaced insulation, wire netting, felt paper, scratch coat and finish coat. Scope of work also included soffit and fascia removal and repairs. Completed February, 2012

Chinle Chapter House – Furnace Repair                                                          Chinle, AZ
Furnished Furnace parts and Furnace Repairs for Chinle Chapter House.  Replace squirrel cages, ignition board. Test Run of repairs to Furnace.  Completed February, 2012

BIA-Jicarilla Agency -- Range Hood Installation for 5 housing units            Dulce, NM
Installed hood ranges for 5 units at Jicarilla/Dulce, NM.  This was for housing improvements on BIA housing compound. Completed January, 2012

APS Four Corners Power Plant – Filters Job & Gasline Repairs               Fruitland, NM
Work included a 3-5 day project to install 30 filter systems at various locations throughout plant complying with EPS standards of protocol. This also included gas leak repair while at site.   Completed January, 2012

APS Four Corners Power Plant – Filters Job                                             Fruitland, NM
Work included a 3-5 day project to install 30 filter systems at various locations throughout plant. This also included gas leak repair while at site.   Completed January, 2012

Leupp Schools, Inc.- FACE Program – Playground and Fencing Installation     Leupp, AZ
Light earthwork and site clearing, grubbing, installation of 237 lf. chain-link fence for new playground site, installation of playground equipment, swing set, timber boarders, and rubber mulch.  Completed March, 2012.

Navajo Housing Authority -- Unit #8 Repairs                  Ojo Amarillo, NM
ZCI performed stucco damage repairs to residential unit #8.  Completed February, 2012.

Navajo Housing Authority -- Unit #22 Repairs                Ojo Amarillo, NM
ZCI performed stucco damage repairs from a fire at one end of the home.  ZCI replaced insulation, wire netting, felt paper, scratch coat and finish coat. Scope of work also included soffit and fascia removal and repairs. Completed February, 2012.

NHA Risk Management – Housing Renovations and Repairs               Mariano Lake, NM
Scope of work included vandalism removal and clean up, included roofing repairs, replacement of roof decking  and new roofing system, insulation installation, plumbing repairs, install HVAC system, electrical wire removal and replacement, interior light fixtures, installation of drywall at interior, tape and texture, prime and paint for interior, removal and replace all windows, installation of cabinetry, remove and replace all interior doors and closet doors, install VCT tile flooring throughout home, installation of all plumbing finishes, interior trim finishes (base boards, etc).  Completed March, 2012.

Navajo Nation Division of Fish & Wildlife – Metal Building Construction         Nenahnezad, NM
This project includes site excavation, installation of a 30’ x 50’ concrete slab with stem walls and piers to support construction of a new commercial metal building located at the Nenahnezad Chapter House property.  Project is ongoing through February, 2012.

NAPI – Region 2 Shop Drywall       Farmington, NM
Drywall repairs were completed to damaged interior drywall.  Completed December, 2011.

NAPI – Fresh Pack Bay Door         Farmington, NM
Twelve foot bay door removal and replacement.  Change order involved replacing damaged supporting door jamb, replacing burned-out motor with new motor, electrical installation, increasing door height by 2 feet, raising and re-welding the header, and replacing existing track assembly to accommodate new door height.  Completed December, 2011.

ZCI, Inc. 2011 Projects


Empire Southwest LLC – Porch Cover Construction      Kayenta, AZ
New porch cover, approximately 10’ width by 54’ length, constructed to provide cover to existing 10’ by 50’ wood deck adjacent to mobile home.  Construction included setting vertical support posts in concrete footers, bolting posts securely to existing structure, roof frame-out, applying roof decking, roofing paper, and pro-panel sections.  Flashing for drip edge trim-out was installed.  Completed December of 2011.

National Park Service/Petrified Forest National Park Visitors Center    Arizona
The National Park Service hired ZCI for window and door renovations for nine staff housing units at the park.  ZCI completed an inventory of existing doors and windows that needed to be replaced.  Old windows were removed, framing was modified to accommodate new window sizes, new energy-efficient windows were installed, finishing was completed along with new exterior paint per specifications.  ZCI crew also replaced the existing French door assemblies with new hardwood French doors, completing reframing as necessary.  The park service also requested that we furnish and install new wooden screen doors at each French door opening.  Completed December, 2011.

BIA- Jicarilla Agency – Interior and Exterior Renovations for Five Houses      Dulce, NM
ZCI furnished all materials and labor to complete extensive renovations for five houses.  Work included new bathroom cabinets, tub/shower enclosures, toilets, drywall and subfloor repairs, plumbing repairs and upgrades, new medicine cabinets, new interior and exterior doors (reframing as required),  new screen doors, new kitchen cabinets, countertops, and sinks, new flooring including carpeting and tile, new energy-efficient windows, taping and texturing drywall, priming and painting interiors and exteriors as required.  Completed December, 2011.

Navajo Office of Youth Development – Backflow Repairs          Fort Defiance, AZ
Emergency call-out for flooding issues at Fort Defiance Youth Development Office.  Back-flow repairs were completed for client.  Completed December, 2011.


NAPI – Fresh Pack Plumbing         Farmington, NM
Emergency call-out for plumbing repairs at NAPI Fresh Pack Building.  Repairs included drain line repairs, installation of new supply lines and vent installation in lavatory (Men’s and Women’s bathrooms).  Completed December, 2011.

Shorty Residence – Sliding Glass Door Replacement                                  Shiprock, NM
ZCI removed and disposed of existing sliding glass door per scope of work.  New header was installed, and frame-out to receive new exterior door.  New Masonite siding and exterior trim-out, new door job extenders and mill set, and new 36” pre-hung exterior door were installed.  Completed November, 2011.

NAPI – Shop Window Installation  Farmington, NM
New frame-out and security window installed.  Completed November, 2011.

Saigan Construction – Window Installation           Canyon de Chelly, Chinle, AZ
ZCI installed a window into an existing metal door at pump house.  Completed November, 2011.

NAPI – Fresh Pack Women’s Restroom    Farmington, NM
The drain line was capped off, and new vent was installed.  Completed November, 2011.

BIA Shiprock Agency – Furnace Removal and Replacement      Shiprock, NM
Scope of project included removal and replacement of a house furnace for Unit #26.  A new 150,000 BTU Rudd furnace was installed, duct work cleaned, plenum replaced and insulated, new thermostat and flexible gas line connection installed.  Job completed November of 2011.

BIA-Jicarilla Agency – New Carpet
ZCI furnished the labor to remove old carpet and pad, and furnished labor and materials to install new broadloom carpet and pad for one residence.  Completed October, 2011.

NAPI – Fresh Pack Office Addition/Remodel       Farmington, NM
Project included construction of two interior walls, including 2 x 4 frame-out, installation of drywall with mudding, tape and texture, primer, and paint.  New slider window, metal door and frame with door swipe, and baseboard installed.  Change order included installation of new utility sink, pex tubing, and drain.  Completed September, 2011.

Benally Residence – Plumbing Repairs       Upper Fruitland, NM
ZCI installed a new residential water heater, and two new ADA toilets.  Completed September, 2011.

NAPI – Region 1 Maintenance Shop Bay Doors   Farmington, NM
Project entailed installation of two new 24’ wide by 18’ high Cornell Service doors, including steel tracks/guides, hardware installation for electric motor operation, and a 3-button system wall station.  New header fabrication and installation of one vertical beam for frame-out adjustment was required.  Completed September, 2011.

APS Four Corners Plant Administration Building – Paint           Fruitland, NM
Materials and labor were furnished by ZCI to paint the power plant government relations liaison office.  Damaged acoustic ceiling tiles were removed and replaced with new tiles, and bent metal grid was repaired.  Completed September, 2011.

APS Four Corners Plant Garage – Cooling Units             Fruitland, NM
ZCI furnished and installed two new large evaporative coolers and two new A/C units at the power plant garage.  The old evaporative coolers and A/C units were removed and disposed of properly.  All units were started and tested for proper function.  Completed September, 2011.

APS Four Corners Plant – Bathroom Repairs      Fruitland, NM
At the 4/5 Building, ZCI furnished and installed a new ADA toilet and replaced VCT floor tiles in the women’s restroom.  Completed August, 2011.

NAPI – Region 2 Grainery Bay Doors       Farmington, NM
This project included installation of four 16’ x 16’commercial overhead doors, tracks, and electric trolley operator.   Completed September, 2011.

NAPI – Executive Office Door        Farmington, NM
ZCI installed a new office door with metal frame-out for executive office.  Completed August, 2011.

NAPI – Farm Operations Stem Wall          Farmington, NM
A concrete stem wall was installed measuring approximately 24’ x 10” x 36” in height to act as a splash guard at the Region 1 Farm Ops Fresh Pack building.  Completed August, 2011.

Nenahnezad Chapter House – Concrete Dumpster Pad   Nenahnezad, NM
ZCI installed an 8’ x 5’ concrete slab for dumpster.  Completed August, 2011.

APS Four Corners Plant – Turbines Phase 2        Fruitland, NM
We furnished all labor and materials to inspect, clean, service, replace parts, and repair two Type 210 VO fan units for air handlers.  Completed August, 2011.

Nenahnezad Chapter House – Mullion Repairs     Nenahnezad, NM
This project included repairs and hinge replacements for three hollow metal doors at the chapter house.  Doors were re-secured to framework and adjusted to function properly. Completed August 2011.

NAPI – Top Office Window Weatherization         Farmington, NM
ZCI removed and replaced energy efficient vinyl windows.  Job included new frame-out and header installation for one window, and installation of insulation, drywall repairs, taping, texturing, priming, and painting.  Two offices received new paint and new cove base.  Completed August, 2011.

Benally Residence – Mobile Home Repair  Upper Fruitland, NM
ZCI crew members re-leveled this mobile home.  Completed August, 2011.

APS Four Corners Plant – Filter and Cartridges Replacement   Fruitland, NM
ZCI provided labor and materials to install filters for the icemakers located in the kitchen and commons area.  Completed  August, 2011.

NAPI – Region 2 Scale House -- General Repairs             Farmington, NM
Installation of one interior door sweep was completed, in addition to bay door electric motor repairs, installation of a door sweep at the bay door, two exterior door sweeps, and adjustment to vertical frame-out at the bay door.  Completed August, 2011.

NAPI – Lab – Vents Farmington, NM
Installed 3 vents in Lab with switches; installed exhaust fans, inspected for lower water flow and minor bathroom renovation work.  All installations were complete with while Lab was in use.  Completed July, 2011.

Newman Residence – Flooring and Plumbing       Bloomfield, NM
All materials and labor were provided by ZCI to install new carpet and pad, new vinyl sheet flooring, and one pedestal sink in the garage apartment.   Completed July, 2011.

Navajo Housing Authority – Unit 13 Repairs        Crystal, NM
Original job scope included repairs to living room wall with removal and replacement of damaged drywall, taping, texturing, priming and painting new surface, and installing and painting new baseboards.  Exterior wall repairs included removal of damaged stucco, realigning the wall framing at damaged site, replacing insulation, installing new stucco finish to match existing exterior finish.  Change order work added to scope included floor tile demo, clean-up and disposal of old damaged floor tiles.  Floor was prepped with removal of old glue, leveling off of chips and cracks on mono slab.  New VCT 12” x 12” tiles installed in professional manner with new transitional strips installed as necessary.  Job completed July of 2011.

NAPI – Main Office – Water Pump Rebuilt and Water Pressure Test   Farmington, NM
Inspection was completed for complaint of low water pressure.  Water pump required repair, the ball valve replaced, and two new gauges were installed.  Completed July, 2011.

APS Four Corners Plant – Turbines Phase 1        Fruitland, NM
ZCI completed extensive inspection, cleaning, maintenance, and repair to eleven sky vents atop the 1-2-3 Turbine Enclosure.  Supply air ducting for enclosure was tested for air leakage and repaired. Completed July 2011.

NAPI – Region 2 Soil Excavation for Utility Conduit Installation           Farmington, NM
NAPI hired ZCI crew to excavate trench for utility conduit installation.  ZCI used backhoe and spotter to complete the project.  Completed July, 2011. 

Benally – House and Swamp Cooler Repairs         Upper Fruitland, NM
ZCI completed repairs to Mr. Benally’s swamp cooler and cooler stand.  Crew also painted the exterior of the house per Mr. Benally’s request.  Completed June, 2011.

O’Donnell Properties --  Drywall Repairs               Farmington, NM
ZCI was hired to complete repairs to damaged drywall inside the Tucker Street apartment complex.  Repairs were completed; drywall was taped, textured, primed, and received two coats of interior paint.  Completed June, 2011.

NAPI – Region 2 -- 10’ by 10’ Storage Shed
ZCI was responsible for purchase, delivery, and set-up of 10’ x 10’ pre-fabricated storage shed to provide temporary shelter and storage at the Region 2 Scale House.  Additional site clearing, earth grubbing, and earth work was included in scope of work.  Completed July of 2011.

NAPI – Main Office Restrooms       Farmington, NM
Emergency service call.  Completed July, 2011.

Navajo Tribal Utility Authority – Energy Audit   Multiple locations on Navajo Reservation, AZ
ZCI teamed with Eaton Corporation to conduct energy audits for residential housing units and commercial structures at multiple designated locations on the Navajo Reservation.  The ZCI team completed audits for 75-plus residential units.  Inspections were conducted for existing insulation, window types and sizes, structure framing, and heating/cooling and water heating units. Completed  July, 2011.

NAPI – Region 2 Shop Bay Door    Farmington, NM
Malfunction located and repairs were completed to the south bay door.  Completed July, 2011.

NAPI – Region 2 Scale House Light Pole Bases Excavation         Farmington, NM
ZCI provided materials and labor to install four commercial light pole concrete bases with embedded anchor bolts.  Completed July, 2011.

NAPI – Region 2 Scale House Drive-Up Ramps Concrete Slabs                         Farmington, NM
NAPI hired ZCI to install two concrete drive-up ramps at the Region 2 Scale House.  The existing ramps had deteriorated and it was unsafe for commercial farm trucks to use them for access to the scale.  Our crew placed the forms, installed required metal reinforcement, and completed the slabs within a one week period.  Completed June, 2011.

APS Four Corners Plant – Warehouse Plumbing Installation     Fruitland, NM
New Pex piping was installed to supply potable water inside the main warehouse procurement offices.  Additionally, ZCI hand excavated several locations in order to locate and reveal an underground valve.  Completed June, 2011.

NAPI – Region 1 I-Beam Repair     Farmington, NM
ZCI provided all labor and materials to remove and replace a damaged 30’ tall steel I-beam located at the Region 2 Hay Barn.  Completed July, 2011.

NAPI – Region 1 Shop Roof Repair           Farmington, NM
Corroded roofing material was removed, along with obsolete, nonfunctioning HVAC units at the Region 1 shop.  New propanel roofing material was installed, all obsolete connections capped off, and any roof penetrations were sealed and caulked.  Completed July, 2011.

NHA Risk Management – Unit 101 Kitchen Remodel and Exterior Stucco       Chinle, AZ
All labor, materials, and equipment were furnished to repair vehicle damage to both the exterior and interior wall of a housing unit.  After demolition of the damaged materials, ZCI crew reframed the damaged wall, installed new insulation, and sheetrock to the interior wall.  Sheetrock was taped, textured, primed and painted to match adjacent interior walls; new baseboards were installed and painted.  Damaged gang boxes, toggle switches, and electrical covers were replaced.  New living room windows were installed after reframing the damaged area.  The entryway received new tiles and a replacement for the damaged magnetic door weather strip.  Completed April, 2011.

NAPI – Region 2 Scale House – Weigh Scale Boot and Fencing  Farmington, NM
ZCI designed and implemented a plan to install a rubber boot on the truck weigh scale to protect the scale from blowing sand and debris.  The sand and debris was causing the scale calibration to malfunction and NAPI officials requested assistance to rectify this reoccurring problem.  ZCI installed a flat bar along the perimeter of the scale, attached the rubber boot to the bar (similar to a table skirt), and arranged to have the scale recalibrated to accommodate the added weight of the boot.  Our crew also constructed a propanel fence to further protect the scale from blowing sand and debris.  Completed June, 2011.

Nenahnezad Chapter House – Exterior Motion-Sensor Lighting            Nenahnezad, NM
ZCI provided and installed twelve commercial grade exterior Lithonia lamps with photo cells.  Completed June, 2011.

Navajo Housing Authority – Unit #33 Interior and Exterior Renovations          Burnside, AZ
ZCI performed extensive renovations on this four bedroom housing unit at the request of NHA.  Work included moderate debris clean-up from previous vandalism; broken window removal and replacement, broken door removal and replacement, new door knobs, deadbolts, and locks installation, new bathroom mirror installation, new fiberglass shower/tub  unit installed, new lighting fixtures and light bulbs installation, replace fire extinguisher and install replacement smoke alarms, install weather-stripping, door sweeps, drywall repairs, texturing, priming, interior paint, caulking, new exterior lights installed, exterior stucco repairs to damaged stucco, new exterior paint, complete turn-key house clean-up for occupancy.  Completed June, 2011.

Navajo Housing Authority – Unit #5 Exterior Gutter Repairs and Stucco Repairs    Steamboat, AZ
All labor, materials, and equipment were provided to make interior and exterior repairs to the wall of a house damaged by a vehicle. Crew replaced damaged wall studs, bottom plate, sill, insulation, and remaining framework of wall; new interior drywall was installed at damage site, taped, textured, and repainted to match existing paint; exterior support wire was replaced and new stucco to match existing stucco was applied.  ZCI replaced the damaged downspout with elbow and painted to match existing color.  Completed May, 2011.

BIA-Jicarilla Agency – Doors, Windows, and Walls         Dulce, NM
ZCI was hired to install new doors for various offices at the Jicarilla Administration Building.  In addition, we installed several new windows, and relocated electrical and water lines to accommodate the installation.  New drywall was installed, taped, textured, and painted for one office.  Completed May, 2011.

NAPI – I.T. Room – HVAC, Wall Condensers, Cooling Units Upgrade            Farmington, NM
Installed duct work, New HVAC System, Wall Condensers, Cooling Units for I.T. Room (computer room). The purpose was to provide client with a controlled temperature environment for computer equipment protection in two locations in the Main Office Building.  Completed May, 2011.

NAPI – Main Office HVAC System            Farmington, NM
This project entailed removal of fourteen heat pump units from the main office building, and installation of an 80,000 BTU heating and 3 ton cooling natural gas system, along with cooling and condensing coils, and adaptation of existing ductwork to marry with newly installed cooling units.  ZCI supplied and installed fourteen new thermostats, installed new gas line from meter to all units, and was responsible for completing roof repairs to maintain the integrity of the existing roofing system.  Completed May, 2011.

Navajo Housing Authority – Housing Drywall and Roofing Repairs      Dilkon, AZ
Completed repairs to damaged roof due to heavy wind and rain. Roof tiles, roofing felt, and roof decking was removed and replaced with similar roofing tile. Because roofing was damaged the interior drywall was damaged as well.  Interior drywall repairs were completed:  removed and replaced drywall, insulation, sanding, texture matched, primed and painted.  Completed April, 2011.

NHA Risk Management – Unit #104 Stucco Repairs             Lukachukai, AZ
Exterior repairs for stucco damage to home.  Work included re-framing interior framework, installing insulation, wall sheathing, felt paper, chicken wire, installation of brown coat, and color coat.  Texture matched, primed and painted.  Interior drywall repairs were also completed:  removed and replaced damaged drywall, installed tape.  Completed April, 2011.

NAPI – Fresh Pack Building Bay Door Repairs    Farmington, NM
This project included all labor, equipment, and materials necessary to install insulated replacement panels for existing 12’ x 24’ overhead doors.  Completed March, 2011.

NAPI – CP Building Bay Door Installation            Farmington, NM
ZCI installed new 12’ x 12’ insulated overhead door with track.  Completed March, 2011.

NAPI – Emergency Water Line Repairs    Farmington, NM
Repairs were completed to a burst water line.  Completed March, 2011.

NAPI – Main Office Boiler Repairs            Farmington, NM
ZCI completed repairs to existing boiler.  Completed February, 2011.

Scott Residence – Thermostat          Shiprock, NM
Troubleshot furnace problem, installed new thermostat, tested for proper function.  February, 2011.

NAPI – 371 Building Heating Repairs and Scale Office HVAC Repairs     Farmington, NM
ZCI installed gas conversion kits, and all heating units inspected for proper operation and start-up.  February, 2011.

NAPI – Farm Ops Bathroom Renovation  Farmington, NM
ZCI completed installation of new Pex line, toilet, drinking fountain, electric heater and heat tap on the main line at the Central Pivot Building.  Electrical work included installation of new 120 volt line, bathroom vent, and reinstallation of hanging light.  Water damaged drywall, framing, baseboards removed, and new framing, drywall, and finish carpentry installed.  New drywall mudded, taped and textured, primed, and painted.  At north end of building, wall frame-out completed, cdx insulation and drywall installed, mudded, taped, textured, primed, painted, including finish trim-out.  New interior door installed.  Job included refurbishing two tabletops with plywood and new Formica top.  Water damage to break-room was repaired with new framing, drywall, window and door repairs, and cove base installation.  Completed January, 2011.

NAPI – Scale House and Ops Buildings Plumbing and HVAC Repairs   Farmington, NM
Excavation to remove and replace gate valve to permit water to flow to OPS Building.Completed January, 2011.

APS Four Corners Plant – Plumbing and Filters Installation      Fruitland, NM
Plumbing repairs for in Maintenance building in men and women’s lavatories, installation of water filters in 22 locations throughout plant.  Involved synchronization of water shut-offs at all locations,  and keeping in compliance with corporate lock-out and tag-out procedures while building in use.  Completed January, 2011.

APS Four Corners Plant – Break Room Paint Job           Fruitland, NM
Performed drywall patch and repairs to APS Break Room.  After drywall repairs, we sanded, textured, primed and painted (two coats). Work performed in a 48-hour time period to accommodate APS staff.  Completed January, 2011.

APS Four Corners Plant – SO2 Control Room Floors, Concrete, Renovations       Fruitland, NM
Job included all demolition work regarding:  removal of flooring tile, flooring penetrations, and removal of acoustical ceiling.  ZCI removed all carpet tile, scraped off old floor glue and removed cove base within room and removed all metal decking on floor surface and within the penetrations where concrete pour took place.  All galvanized metal penetrations were removed and replaced with Vulcraft decking, floor leveling patch was used to patch up any dips, chips, and cracks in floor to prep to receive new VCT floor tile at all locations, including at reinforced areas and filled in penetration.  ZCI, Inc. then installed decking with a qualified and certified welder.  A heat blanket was used to protect wires below the floor surface.  The floor decking was welded into place and the #4 grade 60 rebar was placed 8”o.c. per each penetration.  4000 PSI Concrete ¾” to ½” rock filled in the void along with an accelerant (1% or @% calcium).  Concrete was poured in properly fabricated form, and finished to be level with existing floor surface.  Floor leveler was used to bring continuity of old floor and new pour with a feather finish at 1/20” per 1’ of run, as per specs.  ZCI, Inc. then removed all acoustical ceiling tile and replaced with new ceiling tile as per specs.  Walls were prepped to receive one coat primer and two coats of paint.  Walls were repaired where warranted.  Once painting was completed, ZCI, Inc. installed cove base at perimeter of  room.  Completed January, 2011.

NAPI – Region 1 Scale House Office Furnace and Electrical Repairs    Farmington, NM
New heater filters installed.  Completed January, 2011.

NAPI – Main Office Regulator and Boiler Job      Farmington, NM
ZCI installed a new regulator in existing boiler system.  This included balancing a two-zone system with newly installed regulator & control panel.  Old boiler system had kept shutting down until new regulator was installed.  Job included test runs for proper functioning of unit.  Completed January, 2011.

NAPI – Region 1 Onion Fresh Pack Building Plumbing Repairs            Farmington, NM
ZCI was hired to complete plumbing repairs to an existing bathroom urinal.  Line trap and urinal heights were re-installed at correct heights for proper functioning.  Crew also inspected heater malfunction, corrected pilot safety switch at heat exchanger, replaced transformer, installed White Rodgers gas valve heater, and ran new pilot tubing assembly to new valve.  Completed January, 2011.

Zohnnie Construction Industries, Inc. – Projects prior to 2011.


December 2010.
Pinnacle West Corporation – APS – SO2 Break Room Wall Repairs
Pinnacle West Corporation – APS – SO2 Control Room Floor, Wall, Ceiling Renovation
NAPI – Region 1 OPS Building – Warehouse Heating Unit Upgrade
Farmington Bureau of Land Management Office -- Roof Repair and Heating Unit Repair
Bik’eh Hozho CDC – Tuba City, AZ -- Main Street Conceptual Plan A & E Services

November 2010.
Pinnacle West Corporation – APS – Commons Area Remodel
Farmington Bureau of Land Management Office -- HVAC Repairs
Nenahnezad Chapter House -- HVAC Repairs
Southern Ute Indian Tribe – SunUte Rec Center Solar Units Design and Installation

October 2010.
NHA/Risk Management -- Window Rock, AZ -- Complete Kitchen Renovation
NAPI – Region 1 Top Office -- Bathroom Renovations
NAPI – Office Entry Remodel

September 2010.
NHA/Risk Management – Ojo Amarillo, NM -- Exterior Wall and Stucco Repair
NHA/Risk Management – Becenti, NM -- Exterior Wall and Stucco Repair
Pinnacle West Corporation – APS – Office Interior Paint
Navajo Nation Shopping Center – Shiprock, NM – New Stucco at Bashas Store
NAPI – Region 2 Scale House – New Cabinets and Countertops Installation
Navajo Nation Special Diabetes/Wellness Center – HVAC Units Repair, Cleaning, Testing

August 2010.
NAPI – Region 2 Scale House – Repair Damaged Septic Tank
Nenahnezad Chapter – Veterans Hall Electrical Upgrade
NHA – Lower Greasewood, AZ – 18 Units Stucco Removed and Replaced with New Stucco

July 2010.
NHA – White Cone, AZ – Interior Flooring Installation, Exterior Concrete Drive Pad and Stucco

June 2010.
NAPI – Region 2 – Interior Shop and Office Remodel / Renovation

May 2010.
Navajo Nation Shopping Center – Kayenta, AZ – New Stucco
NAPI – Warehouse – Damaged Pro-Panel Replacement and Skylight Power-wash
Nenahnezad Chapter House – Roof Repairs and Interior Drywall Repairs
NAPI – Region 1 and Main Office – Interior and Exterior Building Upgrades and Repairs

April 2010.
NAPI – Region 2 – Layout, Design, and Construction Drawings for Electrical Distribution/Service

March 2010.
NAPI – IT Office and Valdez Office – Electrical Upgrade, Interior Remodel

January 2010.
NAPI – Potato Fresh Pak Warehouse – Installation of New Updraft Exhaust System
NAPI – Administration Building – HVAC Service and Repairs
O’Donnell Properties – Tucker Apartment Complex – Door Repairs
JBX Five Cattle Company – Cowboy Shack Water Line Repair and Utility Line Excavation
Burnham Dirt Pond – Burnham, NM – Excavation, Site Clearing, Grading, and Compaction
NAPI – Region 1 Shop Galvanized Metal Roofing Repair

Zohnnie Construction Industries, Inc. – Projects prior to 2010.


2009.
Nenahnezad Chapter House – Playground Equipment
Bureau of Indian Affairs / Jicarilla Agency – Residential Housing Renovations (7 Units)
Sanostee Senior Center – Structural Evaluation
NAPI -- Region 1 Shop Roof Repairs and Renovations
NAPI -- Region 2 Scale House Design/Build
NAPI -- Region 2 Main Shop Sewer Line Excavation and Repair
NAPI -- Electrical Building Renovations, including new insulation, siding, paint
NAPI -- Cowboy Shack Interior and Exterior Renovations
NAPI -- Feed Yard Office and Announcer’s Box Interior and Exterior Renovations
NAPI -- Regions 1 and 2 Sewer Line Repairs, Plumbing Upgrades
NAPI -- Farm Operations Building HVAC Installation
NAPI -- Top Office Carpet, Tile, and Paint
NAPI -- ONM Office (Headquarters) Interior Window and Carpet Installation
RIMCO Southwest – Montezuma Creek, UT Satellite Office Plumbing Repairs
NHA – Shiprock Office Building Flooring Installation
Nageezi Senior Citizen Center Interior and Exterior Renovations
Southern Ute Indian Tribe / Sky Ute Casino – Playground Fencing
Solix Bio-Fuels Plant at Southern Ute Indian Reservation – Basin Erection for Bio-Fuel Lagoon
Coyote Gulch Biofuel Feedstock Pilot Project – Interior and Exterior Office Renovations
McKinley County, NM Thoreau Recreational Skate Park Concrete Pad Installation
O’Donnell Properties /Tucker Apartments – Renovations for 5 Units

2008.
Tanis Residence Pro-Panel Roof
SUIT – Water Resources Division – Victor Monte Fencing Installation
SUIT -- Housing Authority Weatherization Project
SUIT -- Piwood and Tamauche Parks Landscaping, Playground, Basketball Court, Picnic Area
SUIT – Bison Pasture Improvement Project -- Irrigation Excavation, Pipe Installation
BIA – Jicarilla Agency Housing (11 Units) Insulation and Plumbing Upgrades
NHA -- Shiprock Agency Housing (15 Units) Excavation and Installation of Water/Sewer Service
NHA – Chilchinbeto, AZ Housing Renovations (18 Units)
NAPI – Fresh Pack Onion Storage Building
NAPI – Fueling Station Concrete Containment Slab
Upper Fruitland Chapter  – Walter Collins Building Roofing and Plumbing Repairs, and Hanta Abatement
Nenahnezad Chapter House  --  Fencing
RIMCO Southwest – Montezuma Creek, UT Satellite Office Roofing , Electrical Upgrade, Drywall, Foundation Repair
Indian Health Service – Dzilth Na O Dith Hle Health Center, NM Sewer Line Repairs